Dependency RAGs are manually updated in BigAgile.
Feature RAGs are automatically determined, based on the rules below .
RAG | Description | Stories | Dependencies |
| Complete | All stories linked to a Feature are done. | All dependencies are done |
| Significant issues | Feature is planned to be completed in the current Sprint but one or more stories are late. | Feature is planned to be completed in the current Sprint but one or more stories are late. |
| Some issues, enough time to address | Feature is planned to be completed in a future Sprint but one or more stories are late.. | One or more dependency is Amber. |
| On track | All underlying stories are planned to be completed in or before the committed completion sprint. | All dependencies for this feature are done or green. |
| Descoped/ deferred | N/A | N/A |